Thursday, October 31, 2013

Framing footings....October 31, 2013


The footings will be sitting on solid rock.  Stacy is drilling into the rock to drive a piece of rebar to restrain the framing lumber.  Slow going but essential.

Given the grade, there are a lot of steps in the footings.  See levels of framing to handle the steps.

Wednesday, October 30, 2013

North Crawl Space and Garage Footings

Boxwood

Stand in the power line cut along side of CR 89 looking west. The job
site is on the brow behind the trees on the far horizon.  I fertilized and
over seeded with the winter rye the park area between the row of stones
and brow.  We're expecting rain later this week.

Boxwood October 30, 2013

If you look closely on the left you can see the preparation for crawl
space footings. This crawl space is under the master bath on the
southeast corner of the house. On the far right you can see
preparation for crawl space footings for the north end. The garage is
located on the north end as well.

Basement Panoramas

If you look closely, you can see the drain pipes buried under the gravel.

Tuesday, October 22, 2013

Framing and Pouring Boxwood Footings

Concrete pump truck used to deliver concrete to all areas of the job
site. Heavy steel in all footings. Fireplace footing (stump)
particularly well reinforced.
More pictures tomorrow.

Basement footings being formed!



Thursday, October 3, 2013

Tuesday, October 1, 2013

Boxwood October 1, 2013

We'll finish the basement dig today. Floor surface will be smoothed
and leveled in preparation for gravel base. Poured wall footings,
walls, and then floor should be poured of the two next week.


Looking North



Looking East







Looking West